Six things have to be confirmed before an industrial X-ray machine arrives: power, any required air supply, footprint, floor loading, environment, and the route from the loading bay to its final position. All six can be checked against the published product-page specifications, which means none of them needs a site survey from the supplier before you start. This applies to conventional offline and inline inspection equipment; it does not cover statutory acceptance, dose measurement or electrical installation work, which belong to the responsible parties on site. Below: what to check on arrival, the first-image baseline to file, the documents to verify, and which acceptance items a user can sign off and which must wait for the manufacturer's engineer.
Work from the published specification, not from a sales drawing, and treat each line as a condition to be confirmed on your own floor. Power is the first one: supply voltage, frequency, phase and the rated load of the system, plus whatever the site's electrical contractor requires for the circuit. Air supply, where a machine uses pneumatics for handling or stage clamping, needs a specified pressure and a clean, dry line. Neither should be discovered on delivery day.
Footprint and floor loading come next. The machine's stated dimensions usually describe the cabinet only; add the space an operator needs to load parts, open doors, swing a monitor arm and reach the emergency stop. Where the system sits on an upper floor or a raised platform, confirm the load with the building engineer. Environment covers temperature, humidity, dust and vibration from neighbouring equipment — a high-magnification cabinet placed next to a press will show it in the images.
Finally, walk the route. Measure door widths, lift capacity, corridor turns and any threshold between the bay and the final position, then compare them with the packed dimensions. An PCB X-ray inspection system destined for an inline position adds conveyor height, upstream and downstream clearance, and board-handling interfaces to this list. Write the six confirmations into one sheet with the person responsible for each; it becomes the first page of the acceptance file.
On arrival, verify identity and condition before anyone signs a delivery note. Check the nameplate model and serial number against the order, confirm the rated electrical data matches the circuit prepared in the previous step, and photograph the crate and any impact indicators before opening.
Compare the packing list with what is actually in the crate: cables, fixtures, test pieces, monitors, manuals and any ordered spare parts.
Inspect the cabinet, door seals, connectors and any glass or leaded viewing window for transport damage.
Check that loose items such as stage fixtures and accessories are present and undamaged; these are listed on the accessories page for the corresponding system.
Record any discrepancy with photographs and the delivery note reference before the crate is disposed of.
Do not power the system to "see if it works" until the incoming checks are complete and the manufacturer's installation conditions are met. An image taken before the machine is levelled and stabilised is not a useful baseline, and a fault introduced during commissioning is much harder to allocate once the packing material is gone. The published X-ray inspection system pages identify the model and its configuration; use them to confirm you received the variant that was ordered.
Capture the first image under the same fixed conditions that the daily image-quality check will use for the life of the machine. That is what makes the installation record useful: every later shift compares back to this one, so a slow detector drift or a change in geometry has a reference point.
Use a stable test piece at a marked position, and record tube voltage, current, magnification, grey window, detector correction state, the date, and who took the image. File the image itself, not just the numbers. If the manufacturer's engineer establishes the settings during commissioning, get those values written into the record at the time rather than reconstructing them weeks later.
This baseline is an image-consistency record, not a calibration certificate. The site's guide on X-ray calibration and maintenance sets out what an operator's check can and cannot establish. Linking the installation baseline to that procedure closes the loop: the day the machine was accepted becomes day one of the maintenance log.
Verify that the documents and indications that should accompany the machine are present and match the delivered model; do not assume them from a brochure or a certificate shown during the sales process. The checklist is about presence and correspondence, not about measuring anything.
Operating manual and any safety instructions in a language the operators on site can read.
Declaration or certificate documents supplied with the equipment, with model and serial number matching the nameplate.
Warning labels, interlock and emergency-stop indications, and a documented function check performed with the commissioning engineer.
The site's own radiation-safety documentation, where local rules require it, and the name of the responsible person.
Keep copies in the acceptance file and note which items were physically checked. This page makes no claim about dose values, shielding performance or regulatory compliance — those are established by the competent parties under the requirements that apply to your site. What a user can do at installation is make sure the paperwork exists, is for this machine, and has been read by the people who will operate it.
Split the acceptance list into things a user can verify from the delivered equipment and things that require the manufacturer's engineer or a competent external body. Signing the whole sheet at once is how open items quietly become the user's responsibility.
Acceptance items grouped by who can close them
Item | Who closes it | Evidence to file |
Model, serial number, delivered configuration | User, at unpacking | Nameplate photo against order and packing list |
Site conditions: power, air, footprint, load, route | User with site engineer | Completed six-point sheet |
First-image baseline and settings | User with commissioning engineer | Image plus recorded conditions |
Interlock and indicator function check | Manufacturer's engineer, witnessed by user | Signed commissioning record |
Statutory or regulatory acceptance, where applicable | Competent external body | Formal document, referenced in the file |
Performance against the ordered specification | Manufacturer's engineer, witnessed by user | Demonstration on the user's own part |
Defer the last rows explicitly if they cannot be closed on the day, with a date and an owner. A delivery of an X-ray inspection machine is not an acceptance of its imaging performance until it has produced an image of your part under agreed conditions. Where a demonstration uses the supplier's sample instead, say so in the record.
Most installation problems are ordinary logistics, not technical failures. Order them by the cost of discovering them late.
The route was never walked. A cabinet that fits the room but not the door or the lift turns into dismantling, re-crating and a second delivery date.
Footprint measured on the cabinet alone. Door swing, operator position and monitor arm were not included; the machine works but nobody can load a board comfortably.
Power confirmed only as "we have a socket". Rated load, phase and earthing are checked after the engineer arrives, which loses the commissioning slot.
No first-image baseline. Six months later nobody can tell whether a change in image quality is drift, a settings change or a service adjustment.
Everything signed at once. Interlock checks and statutory items are marked complete before they are actually performed, leaving no record of who owes what.
Inline interfaces left to the last week. Conveyor height and handshakes with upstream equipment are discovered during installation, when changing them is most expensive.
Each of these is preventable with the six-point sheet and a split acceptance list. Neither requires any supplier data beyond the published specification and the documents delivered with the machine.
Sometimes, but check what the published dimensions exclude. Clearance for doors, operator access, service panels and interlock-related restrictions all have to remain. Confirm any change with the manufacturer before moving walls or building a platform; a dimension that looks marginal on paper may be fixed by the machine's design.
Ideally the operator who will run the daily check, with the commissioning engineer present to confirm the settings. That way the baseline belongs to the site's own procedure from day one rather than being a service image nobody can reproduce.
For as long as your quality system requires, and normally for the service life of the machine. The baseline image, the settings used to make it and the commissioning record stay useful for as long as anyone needs to compare a later image against the day the machine was accepted.
Seamark ZM published product pages: offline X-ray inspection machine, X1200 offline system, online X-ray inspection machine, microfocus X-ray inspection machine, and accessories. Site conditions in this article are described as fields to confirm against those pages; no numeric values are asserted.
The equipment's own operating, installation and safety documentation, and the site's applicable regulatory requirements, take precedence over any general checklist.
Internal guides on this site: maintenance and calibration of industrial X-ray machines, and the daily image-quality baseline procedure.